The appellate decision arose from two separate challenges below. The “Atherton I” petitioners had secured a partial victory in their challenge to the Authority’s revised final PEIR, which was the product of a successful challenge to the “original” final PEIR: the trial court ruled that the revised final PEIR failed to adequately address the traffic impacts of narrowing and moving Monterey Highway to accommodate the Pacheco Pass alignment for the HST.
However, the trial court rejected the Atherton I petitioners’ other CEQA challenges, holding that it was proper for the Authority to defer analysis of certain vertical profile alignment impacts—relating to the elevation of track above ground level—until a later project-specific EIR. The court also held that petitioners’ challenge to information contained in the project description that was based on an allegedly flawed revenue and ridership model reflected a “classic disagreement among experts that often occurs in the CEQA context” and did not provide a basis for invalidating the PEIR.
- it provided an inadequate analysis of the “vertical profile options for alignment” along portions of the San Francisco Peninsula;
- it used a flawed revenue and ridership model that improperly skewed the results in favor of the Pacheco Pass alternative for connecting the Central Valley to the San Francisco Bay Area, rather than the Altamont Pass alternative further to the north; and
- the range of alternatives analyzed was inadequate.
Finally, the court held that the Authority analyzed an adequate range of alternatives and was not required to evaluate additional alternatives proposed by petitioners, based on one of the following findings:
- the claim was barred by collateral estoppel;
- the alternative was substantially similar to one of those evaluated in the revised final PEIR;
- the alternative would continue to be studied at the project level; or
- the Authority’s infeasibility findings were supported by substantial evidence.
This will probably not be the last of the CEQA challenges facing the HST. A petition for review by the Supreme Court is likely. Also, because the court of appeal affirmed the trial court’s issuance of a supplemental peremptory writ and ordered the Authority to set aside its approval of the revised final PEIR to correct deficient traffic analyses, additional challenges may follow issuance of a (further) revised final PEIR with respect to that issue. Finally, any project-level EIRs prepared for the HST may also face CEQA challenges.
--Don Sobelman and Nicole Martin
For more information, contact Don Sobelman at (415) 228-5456 or des@bcltlaw.com; or Nicole Martin at (415) 228-5435 or nmm@bcltlaw.com.
No comments:
Post a Comment